|
Claim & Counter-Claim Management Workshop
and Negotiating Win-Win Settlement
Multi-Discipline Issues of Concern to Claim Professionals
A
2 week Training Program & Workshop
Program & Workshop Schedule
|
Worldwide Training Dates |
USA Training Schedule |
|
|
-
7-18 Sept 08 (San Francisco)
-
15-26 Dec 08 (San Francisco)
-
12-23 Dec 08 (San Francisco)
-
26 Dec - 6 Jan 09 (New York)
|
Program Overview
Claims are common on Construction, Service and Maintenance Projects. 99.99% of
these get sorted out through negotiations. The negotiated settlements depend
on the effectiveness of the negotiation preparation process in your
organization. Preparation for negotiations must essentially follow the same
methodology as for resolving the dispute in a court of law or arbitration.
Simplistic view of claims is dangerous - it often leads to insufficient
protection of your organization's interests.
This Program Can Save Your Organization
Substantial Sums which would have been paid as Claims, Delays and Consultant
Fees. Claims are Changes in Contract Works whose Liability, Cause or Impact
have not been agreed between the Owner and the Contractor. The Claimant has
the burden of proving the Liability, the Impact of this Liability Action and
the Additional Costs suffered as a consequence. Calculating time impact and
additional allowable costs is an important area covered in this program. The
Claimant and the party analyzing the claim loose large sums due to default
caused by not understanding the calculation methods available and their legal
acceptability as a reasonable proof. Also covered are the Concurrent events
mitigation responsibilities because of their impact on Allowable Additional
Costs.
Claims are Changes in Contract Works whose Liability, Cause or
Impact have not been agreed between the Owner and the Contractor. The Claimant
has the burden of proving the Liability, the Impact of this Liability Action
and the Additional Costs suffered as a consequence. Calculating time impact
and additional allowable costs is an important area. The Claimant and the
party analyzing the claim loose large sums due to default caused by not
understanding the calculation methods available and their legal acceptability
as a reasonable proof. Also covered are the Concurrent events mitigation
responsibilities because of their impact on Allowable Additional Costs.
This is a Best Industry
Practice Program...
This program helps you identifying what are the industry
best practices, and understanding how we will implement similar practices in
our organization.
Who Should Attend?
All Professionals Working for Engineering, Construction, Services, Purchase or
Maintenance Contracts. It will also be extremely useful for Project Managers,
Project Lawyers, Quantity Surveyors, Contract Administrators, Coordinators,
Engineering Department Managers, Purchase Managers, Planning Engineers and
Senior Executives.
Prerequisites and Program Pre-Preparation
This
program is in English. The participant should understand spoken English. If you wish to study the program materials before the program these can be obtained by payment of half the program fee. Whenever you attend a deduction of this amount will be allowed from payable program fee. Please note this offer is available only to Corporate Customers.
Certificate of Participation and
Completion:-
On
completion participants will be awarded a "Certificate of Successful
Completion".
Program Instructor may decide to award a Letter of Recommendation for High
Performers during the program.
Program & Workshop Content
-
What are Claims?
-
What are Counter-Claims?
-
Disputed Variation Orders
-
Constructive Changes: Increased Performance Requirements:-
-
Delays, Acceleration, Deceleration, Interruptions, Unit Price Manipulations,
Quantity Revisions, Value Engineering Clause Changes, Premium Time, Owner
Furnished Materials and Equipment, Access to Site, Working Conditions,
Quality of Workmanship, Defective Work, Weather Water, Loss of Efficiency,
Discrepancies in Plans Specifications, Drawing Errors, Wasted Effort,
Escalation, Emergency Work, Out of Scope Changes, Suspension of Work,
Termination for Breach, Termination for Convenience, Denial of Early
Completion, Improper Rejection, Denial of Time Extension, Out of Sequence
Work, Defective Specifications, Ambiguities, Idle Resources (men and
equipment), Failure to Approve Timely, Failure to Approve, Wrongful
Rejection, Moving Resources, Design Errors, Revised Owner Requirements,
Engineering Cost, Reengineering Costs, Failure to Pay, Improper Rejection,
Out of Season Work.
-
Fundamental Principles Involved in Claims:
-
Proving Liability : Legal Basis of Right - Contractual Clause or Implied,
Proving Breach has Occurred, Notices, Form for Proving Liability in
Preparation and Evaluation Claim Document.
-
Proving Causation : Connection Between Change and Cost Increase. Tools and
Techniques Available. Form for Proving Causation in Preparing and
Evaluating Claim Document.
-
Proving Damages and Injury Caused (Quantified): Methods for Quantification
of Damages and Injury.
-
Standard of Proof Required: Preponderance Standard.
-
Causation. Checking Causation Evidence to Enable a Rebuttal of Contractor’s
Claim. Causation is Linking “Liability” to Disruptive Occurrence. Proof of
Causation requires proof of the connection between the “change” and the
“delay in completion and/or cost increase”.
-
Tools and Methods for Showing and/or Checking for Satisfactory “Causation”
Proof : Schedules, Critical Path Method (CPM), As-built Schedules, Expert
Witness. How to Prove Linkage between “Liability” and Resultant “Injury or
Damages” that May be Caused including Delay, Disruption of Work,
Interference, Inefficiency, Acceleration, Constructive Acceleration,
Productivity Loss, Mobilization, Re-mobilization, Concurrent Working, Idle
Resources, Additional Storage, Price and Labor
Escalation, Unavailability of Skilled Manpower, Ripple Effect, Overtime
Working, Procurement Costs, Inefficient Use of Resources, Injury to Workmen.
etc..
-
Recovery of Claim Damages/Loss : A Claim Settlement is proper when it leaves
the contractor and the owner in the same relative cost and profit (or loss)
positions they would have occupied had there been no change. Profit on the
unchanged work remains intact. The party liable for the change keeps the
other party whole.
-
Quantification Methods for Claims: Lowest Possible Price, Lowest Reasonable
Price, Reasonable Price, Estimated Price, Actual Cost, Fair Market Value,
Contractor’s Current Cost or Pricing Data, Contractor’s Tender Breakdown,
Formula Pricing vs Total Pricing, Work Methods Used. Dealing with : Honest
Mistakes and Errors, Exercise of Discretion, Deleted Work, Contractor’s Low
Cost Innovations, B.O.Q., Unbalanced Bid Items, Overhead, Profit,
Subcontractor’s Works, Specific Contractual Limitations on Recovery, Special
Damages, Defective Performance, Commercial Waste, Claim Presentation
Expenses, Total Cost Approach, Total Productivity Loss Approach, Expert
Witness Method.
-
Preparing Analyzing the Claim Document: Skills in Putting the Claim
Document Together as well as Pulling It Apart. Effective Presentation,
Checklists, Getting Ideas.
-
Steps in the Claim Preparation Process. Preparation and Analyzing: Quality
Assurance in Preparation and Analyzing Plans.
-
Effective Presentation of Claims and Counter Claims. Arbitration :
Provisions and Procedures. Benefits and Economics of Negotiated Settlements,
Win-Win Philosophy.
-
Negotiated Settlement of the Claim: Each party has “expectations” linked
directly to its own perception of one’s and other’s strong and weak points.
You have the job to change the “expectations” of the other party - How
Expectations can be Changed?
-
Pre-Negotiation Planning : Detail requirements and analysis of the
contractor’s estimate. Contractor’s cost and price data. Audit of
Contractor’s cost data. Preparing independent estimates. Sources for
independent estimates. Establishing flexible negotiation strategies.
-
Conducting Negotiations. Some Effective Negotiation Tactics and Tricks
People Use : Consider using them, Countering them.
-
Workshop : Hands on Claims Preparation & Analysis
For
Latest Program Schedule Email:
cpp305@EuroTraining.com
Registration Recommendations
It is
recommended you nominate two participants together for this program.
Single
nominations will also be considered.
REGISTRATION
INFORMATION
-
Please complete the Registration Form (Available at http://www.eurotraining.com/etl-reg.html) and FAX
to UK +44 207 6811444 or Email to:
euro@eurotraining.com
-
Fee is £3900 (USD $7800) per participant includes Course Materials, Certificate,
Refreshments and Lunch.
-
Accommodation is not included in Program fee.
Special rates will be available at venue hotel for the participants.
-
Program Fee information is available by
Emailing: fees@eurotraining.com. Fee is payable by Bank Transfer or
Bank Draft in favor of the local representative office.
-
Early Registration & Payment discount is 10% -
if registration and fee payment is made at least 45 days before start of the program.
-
Fee includes Course Materials, Certificate/s, Refreshments and Lunch. Program Timings are 8:30 AM to 2:30 PM but on some days (to be announced by instructor/s) you may be asked to attend from 3:00 PM to 7:30 PM. For First Day Program Timings see your Joining Instructions.
Claim & Counter-Claim Management Workshop and Negotiating Win-Win Settlement Multi-Discipline Issues of Concern to Claim Professionals
CPP305
Contact:
Mr Harry Miller, General Manager
FAX (UK) Fax : +44 207 6811444
FAX (USA) +1 650 6492689
UAE Dubai Fax +971 84
481032
www.EuroTraining.com
www.EuroTrainingUK.com
Email:
euro@eurotraining.com
or
euro@eurotraining.com
Registration Form available at http://www.eurotraining.com/etl-regn.html
More Training Programs...
2008
2009
Auditing
CAD-EDMS
Contracts
ENERGY
ENGINEERING
Environment
Finance
HRD
Intellectual Property
IT
Knowledge Management
Maintenance
Management Marketing
Petroleum Industry
Project
Procurement
Quality
Safety
Registration INFO
Registration Form
Fee Schedule
About
Euro Training Limited & Programs
www.EuroTraining.com
www.EuroTrainingUK.com
|