|
Claims
Management
And Negotiating Win-Win Settlements
Effective Win-Win Strategy
That Keeps
Business Relationships Intact
On Engineering, Construction, Services, Supply
Maintenance Contracts
A
1 week Training Program
Program Schedule
|
Worldwide Training Dates |
USA Training Schedule |
|
|
-
7-11 Sept 08 (San Francisco)
-
3-7 Oct 08 (Washington, DC)
-
15-19 Dec 08 (San Francisco)
-
26 - 30 Dec 08 (New York)
|
Program Overview
-
This Program Can Save Your
Organization Substantial Sums which would have been paid as Consultant Fees
and Claims.
-
Claims are Changes in Contract Works
whose Liability, Cause or Impact have not been agreed between the Owner and
the Contractor.
-
The Claimant has the burden of proving
the Liability, the Impact of this Liability Action and the Additional Costs
suffered as a consequence.
-
Calculating time impact and additional
allowable costs is an important area where both the Claimant and the party
analyzing the claim often loose large sums due to default caused by not
understanding the calculation methods available and their acceptability as
reasonable way of doing the same.
-
Also very
important are the Concurrent Events and Mitigation responsibilities because
of their impact on Allowable Additional Costs.
-
This Program provides you the training in how
to:
Prepare, Quantify, Prove, Defend and Successfully Negotiate Claims.
-
After attending the
Participant will also be able to :
-
Objectively Preserve and Support the Relevant Facts.
-
Analyze Claims Submitted.
-
Negotiate and Settle Expeditiously Claims on the
Contract
-
Contrary to popular
belief among Contract and Engineering Professionals the Contractor is not
entitled to Additional Payment just because an Owner Caused Delay or Default
has Occurred on the Contract. For
Entitlement the Claiment Must Satisfactorily Prove ALL the Following:
-
Liability : Legal Basis of
Right
-
Causation : Connection Between Change and Cost Increase.
-
Damages and Loss Caused
-
Damages have been Mitigated
-
This program will show you how all above are
Established, Analyzed and Argued during Negotiations or Legal Proceedings.
Who Should Attend?
All Contract, Procurement Project Professionals
Working for Engineering, Construction, Services, Purchase or Maintenance
Contracts. It will also be extremely useful for Claim Consultants, Project
Managers, Project Lawyers, Quantity Surveyors, Contract Administrators,
Project Coordinators, Engineering Department Managers, Purchase Managers,
Planning Engineers, Managers and Senior Executives.
Prerequisites and Program Pre-Preparation
This
program is in English. The participant should understand spoken English. If you wish to study the program materials before the program these can be obtained by payment of half the program fee. Whenever you attend a deduction of this amount will be allowed from payable program fee. Please note this offer is available only to Corporate Customers.
Certificate of
Participation and Completion:-
On
completion participants will be awarded a "Certificate of Successful
Completion".
Program Instructor may decide to award a Letter of Recommendation for High
Performers during the program.
Program Style
This Program Presents Easy to Implement Practical
Procedures and Checklists Approach to Solving Claims Related Problems.
Discussion, Implementation and Case Studies will be based on conditions
prevailing in the Gulf Region.
Program Content
-
Balanced Score-card for Claims Management & Settlement Professionals
-
Understanding Claims
-
The Right to Claim and Counter Claims
-
Win-Win Settlement Strategy
-
Systematic Analysis & Defence of Claims: Liability, Causation & Damage
-
Setting Up an Early Warning System for Potential Claim Identification
-
Understanding the Liability Concept in Law
-
Analyzing Liability Proof
-
Defending Against Liability Claim (CHECKLIST)
-
Collecting Evidence to Prove Liability (CHECKLIST)
-
Understanding Causation (Proving Definite Link between Claim Event & Claimed
Damage)
-
Analyzing Causation Evidence Presented (CHECKLIST)
-
Owner's Defence against Causation Proof in Claim (CHECKLIST)
-
Collecting Causation Refutation Evidence during Project (CHECKLIST)
-
Understanding Legally Acceptable Methods for Calculating Damages in Claims
-
What damages are Claimable (CHECKLIST)
-
Mitigation Responsibility of the Claimant
-
Typical Methods of Inflating Claim Calculations and How to Identify them
(Detailed Procedures)
-
Collecting Evidence to Establish, Analyze and Refute Inflated Claim
Calculations
-
Understanding the Claims Resolution Process (99.99% of Claims Get Settled
this Way)
-
Negotiating Strategies for Claims
-
An Action Plan you can Implement to Minimize Unjustified Claims
Topics Covered Include....
-
Constructive Changes – Changes that
could lead to a Potential Claim: Understanding the Increased Performance
Requirements in case of:-
-
Delays
-
Acceleration
-
Deceleration
-
Interruptions
-
Unit Price Manipulations
-
Quantity Revisions
-
Value Engineering Clause Changes
-
Premium Time
-
Owner Furnished Materials and Equipment
-
Access to Site
-
Working Conditions
-
Quality of Workmanship
-
Defective Work
-
Weather Water
-
Loss of Efficiency
-
Discrepancies in Plans Specifications
-
Drawing Errors
-
Wasted Effort
-
Escalation
-
Emergency Work
-
Out of Scope Changes
-
Suspension of Work
-
Termination for Breach
-
Termination for Convenience
-
Denial of Early Completion
-
Improper Rejection
-
Denial of Time Extension
-
Out of Sequence Work
-
Defective Specifications
-
Ambiguities
-
Idle Resources (men and equipment)
-
Failure to Approve Timely
-
Failure to Approve
-
Wrongful Rejection
-
Moving Resources
-
Design Errors
-
Revised Owner Requirements
-
Engineering Cost
-
Reengineering Costs
-
Failure to Pay
-
Improper Rejection
-
Out of Season Work.
-
Causation.
-
Tools and Methods for Showing and/or
Checking for Satisfactory “Causation” Proof :
Schedules
Critical Path Method (CPM)
As-built Schedules
Expert Witness.
-
Recovery of Claim Damages/Loss : A
Claim Settlement is proper when it leaves the contractor and the owner in
the same relative cost and profit (or loss) positions they would have
occupied had there been no change. Profit on the unchanged work remains
intact. The party liable for the change keeps the other party whole.
-
Quantification Methods for Claims:
-
Lowest Possible Price
-
Lowest Reasonable Price
-
Reasonable Price
-
Estimated Price
-
Actual Cost
-
Fair Market Value
-
Contractor’s Current Cost or Pricing Data
-
Contractor’s Tender Breakdown
-
Formula Pricing vs Total Pricing
-
Work Methods Used.
-
Impact on Claimed Amount of:
-
Honest Mistakes and Errors
-
Exercise of Discretion
-
Deleted Work
-
Contractor’s Low Cost Innovations
-
B.O.Q. Unbalanced Bid Items
-
Overhead
-
Profit
-
Subcontractor’s Works
-
Specific Contractual Limitations on Recovery
-
Special Damages
-
Defective Performance
-
Commercial Waste
-
Claim Presentation Expenses
-
Total Cost Approach
-
Total Productivity Loss Approach
-
Expert Witness Method.
-
Preparing Analyzing the Claim
Document: Skills in Putting the Claim Document Together as well as Pulling
It Apart.
-
Effective Presentation, Checklists,
Getting Ideas.
-
Steps in the Claim and Counter-Claim
Preparation Process. Preparation and Analyzing: Quality Assurance in
Preparation and Analyzing Plans. Establishing: Liability, Causation and
Proving Damages.
-
Effective Presentation of Claims and
Counter Claims. Arbitration : Provisions and Procedures. Benefits and
Economics of Negotiated Settlements, Win-Win Philosophy.
-
Negotiated Settlement of the Claim:
Each party has “expectations” linked directly to its own perception of one’s
and other’s strong and weak points. You have the job to change the
“expectations” of the other party - How Expectations can be Changed?
-
Pre-Negotiation Planning : Detail
requirements and analysis of the contractor’s estimate. Contractor’s cost
and price data. Audit of Contractor’s cost data. Preparing independent
estimates. Sources for independent estimates. Establishing flexible
negotiation strategies.
-
Conducting Negotiations. Steps in
Negotiation.
-
Some Effective Negotiation Tactics
and Tricks People Use : Consider using them, Countering them.
For Latest Program
Schedule Email:
cpp304@EuroTraining.com
REGISTRATION
INFORMATION
-
Please complete the Registration Form (Available at http://www.eurotraining.com/etl-reg.html) and FAX
to UK +44 207 6811444 or Email to:
euro@eurotraining.com
-
Fee is £2250 (USD 4200) per participant includes Course Materials, Certificate,
Refreshments and Lunch.
-
Accommodation is not included in Program fee.
Special rates will be available at venue hotel for the participants.
-
Program Fee information is available by
Emailing: fees@eurotraining.com. Fee is payable by Bank Transfer or
Bank Draft in favor of the local representative office.
-
Early Registration & Payment discount is 10% -
if registration and fee payment is made at least 45 days before start of the program.
-
Fee includes Course Materials, Certificate/s, Refreshments and Lunch. Program Timings are 8:30 AM to 2:30 PM but on some days (to be announced by instructor/s) you may be asked to attend from 3:00 PM to 7:30 PM. For First Day Program Timings see your Joining Instructions.
Claims
Management
And Negotiating Win-Win Settlements
CPP304
Contact:
Mr Harry Miller, General Manager
FAX (UK) Fax : +44 207 6811444
FAX (USA) +1 650 6492689
UAE Dubai Fax +971 84
481032
www.EuroTraining.com
www.EuroTrainingUK.com
Email:
euro@eurotraining.com
or
euro@eurotraining.com
Registration Form available at http://www.eurotraining.com/etl-regn.html
More Training Programs...
2008
2009
Auditing
CAD-EDMS
Contracts
ENERGY
ENGINEERING
Environment
Finance
HRD
Intellectual Property
IT
Knowledge Management
Maintenance
Management Marketing
Petroleum Industry
Project
Procurement
Quality
Safety
Registration INFO
Registration Form
Fee Schedule
About
Euro Training Limited & Programs
www.EuroTraining.com
www.EuroTrainingUK.com
|