Best Training You Can Attend - A Lifetime Benefit

Euro Training Programs Incorporate Quality Assurance Current Best Practices ! ETL is Commited to ISO-9000 TQM. Best Training You Can Attend!!

Claims Management

And Negotiating Win-Win Settlements

Effective Win-Win Strategy

That Keeps Business Relationships Intact

On Engineering, Construction, Services, Supply Maintenance Contracts

A VERY PRACTICAL PROGRAM

A 1 week Training Program

Program Schedule

Worldwide Training Dates USA Training Schedule
  • 12-16 Oct 2008 (London)

  • 7-11 Nov 2008 (Kula Lumpur)

  • 20 - 24 Nov 2008 (Dubai)

  • 8-12 Jan 2009 (Dubai)

  • 7-11 Sept 08 (San Francisco)
  • 3-7 Oct 08 (Washington, DC)
  • 15-19 Dec 08 (San Francisco)
  • 26 - 30 Dec 08 (New York)

Program Overview

  • This Program Can Save Your Organization Substantial Sums which would have been paid as Consultant Fees and Claims.

  • Claims are Changes in Contract Works whose Liability, Cause or Impact have not been agreed between the Owner and the Contractor.

  • The Claimant has the burden of proving the Liability, the Impact of this Liability Action and the Additional Costs suffered as a consequence.

  • Calculating time impact and additional allowable costs is an important area where both the Claimant and the party analyzing the claim often loose large sums due to default caused by not understanding the calculation methods available and their acceptability as reasonable way of doing the same.

  • Also very important are the Concurrent Events and Mitigation responsibilities because of their impact on Allowable Additional Costs.

  • This Program provides you the training in how to: Prepare, Quantify, Prove, Defend and Successfully Negotiate Claims.

  • After attending the Participant will also be able to :

    • Objectively Preserve and Support the Relevant Facts.

    • Analyze Claims Submitted.

    • Negotiate and Settle Expeditiously Claims on the Contract

  • Contrary to popular belief among Contract and Engineering Professionals the Contractor is not entitled to Additional Payment just because an Owner Caused Delay or Default has Occurred on the Contract. For Entitlement the Claiment Must Satisfactorily Prove ALL the Following:

    • Liability : Legal Basis of Right

    • Causation : Connection Between Change and Cost Increase.

    • Damages and Loss Caused

    • Damages have been Mitigated

  • This program will show you how all above are Established, Analyzed and Argued during Negotiations or Legal Proceedings.

Who Should Attend?

All Contract, Procurement Project Professionals Working for Engineering, Construction, Services, Purchase or Maintenance Contracts. It will also be extremely useful for Claim Consultants, Project Managers, Project Lawyers, Quantity Surveyors, Contract Administrators, Project Coordinators, Engineering Department Managers, Purchase Managers, Planning Engineers, Managers and Senior Executives.

Prerequisites and Program Pre-Preparation

This program is in English. The participant should understand spoken English. If you wish to study the program materials before the program these can be obtained by payment of half the program fee. Whenever you attend a deduction of this amount will be allowed from payable program fee. Please note this offer is available only to Corporate Customers.

Certificate of Participation and Completion:-

On completion participants will be awarded a "Certificate of Successful Completion".
Program Instructor may decide to award a Letter of Recommendation for High Performers during the program.
 

Program Style

This Program Presents Easy to Implement Practical Procedures and Checklists Approach to Solving Claims Related Problems. Discussion, Implementation and Case Studies will be based on conditions prevailing in the Gulf Region.

Program Content

  • Balanced Score-card for Claims Management & Settlement Professionals

  • Understanding Claims

  • The Right to Claim and Counter Claims

  • Win-Win Settlement Strategy

  • Systematic Analysis & Defence of Claims: Liability, Causation & Damage

  • Setting Up an Early Warning System for Potential Claim Identification

  • Understanding the Liability Concept in Law

  • Analyzing Liability Proof

  • Defending Against Liability Claim (CHECKLIST)

  • Collecting Evidence to Prove Liability (CHECKLIST)

  • Understanding Causation (Proving Definite Link between Claim Event & Claimed Damage)

  • Analyzing Causation Evidence Presented (CHECKLIST)

  • Owner's Defence against Causation Proof  in Claim (CHECKLIST)

  • Collecting Causation Refutation Evidence during Project (CHECKLIST)

  • Understanding Legally Acceptable Methods for Calculating Damages in Claims

  • What damages are Claimable (CHECKLIST)

  • Mitigation Responsibility of the Claimant

  • Typical Methods of Inflating Claim Calculations and How to Identify them (Detailed Procedures)

  • Collecting Evidence to Establish, Analyze and Refute Inflated Claim Calculations

  • Understanding the Claims Resolution Process (99.99% of Claims Get Settled this Way)

  • Negotiating Strategies for Claims

  • An Action Plan you can Implement to Minimize Unjustified Claims

 

Topics Covered Include....

  • Constructive Changes – Changes that could lead to a Potential Claim: Understanding the Increased Performance Requirements in case of:-

    • Delays

    • Acceleration

    • Deceleration

    • Interruptions

    • Unit Price Manipulations

    • Quantity Revisions

    • Value Engineering Clause Changes

    • Premium Time

    • Owner Furnished Materials and Equipment

    • Access to Site

    • Working Conditions

    • Quality of Workmanship

    • Defective Work

    • Weather Water

    • Loss of Efficiency

    • Discrepancies in Plans Specifications

    • Drawing Errors

    • Wasted Effort

    • Escalation

    • Emergency Work

    • Out of Scope Changes

    • Suspension of Work

    • Termination for Breach

    • Termination for Convenience

    • Denial of Early Completion

    • Improper Rejection

    • Denial of Time Extension

    • Out of Sequence Work

    • Defective Specifications

    • Ambiguities

    • Idle Resources (men and equipment)

    • Failure to Approve Timely

    • Failure to Approve

    • Wrongful Rejection

    • Moving Resources

    • Design Errors

    • Revised Owner Requirements

    • Engineering Cost

    • Reengineering Costs

    • Failure to Pay

    • Improper Rejection

    • Out of Season Work.

  • Causation.

    • Proof of Causation requires proof of the connection between the “change” and the “delay in completion and/or cost increase”.

    • Checking Causation Evidence to Enable a Rebuttal of Contractor’s Claim.

  • Tools and Methods for Showing and/or Checking for Satisfactory “Causation” Proof :

Schedules

Critical Path Method (CPM)

As-built Schedules

Expert Witness.

  • Recovery of Claim Damages/Loss : A Claim Settlement is proper when it leaves the contractor and the owner in the same relative cost and profit (or loss) positions they would have occupied had there been no change. Profit on the unchanged work remains intact. The party liable for the change keeps the other party whole.

  • Quantification Methods for Claims:

    • Lowest Possible Price

    • Lowest Reasonable Price

    • Reasonable Price

    • Estimated Price

    • Actual Cost

    • Fair Market Value

    • Contractor’s Current Cost or Pricing Data

    • Contractor’s Tender Breakdown

    • Formula Pricing vs Total Pricing

    • Work Methods Used.

  • Impact on Claimed Amount of:

    • Honest Mistakes and Errors

    • Exercise of Discretion

    • Deleted Work

    • Contractor’s Low Cost Innovations

    • B.O.Q. Unbalanced Bid Items

    • Overhead

    • Profit

    • Subcontractor’s Works

    • Specific Contractual Limitations on Recovery

    • Special Damages

    • Defective Performance

    • Commercial Waste

    • Claim Presentation Expenses

    • Total Cost Approach

    • Total Productivity Loss Approach

    • Expert Witness Method.

  • Preparing Analyzing the Claim Document: Skills in Putting the Claim Document Together as well as Pulling It Apart.

  • Effective Presentation, Checklists, Getting Ideas.

  • Steps in the Claim and Counter-Claim Preparation Process. Preparation and Analyzing: Quality Assurance in Preparation and Analyzing Plans. Establishing: Liability, Causation and Proving Damages.

  • Effective Presentation of Claims and Counter Claims. Arbitration : Provisions and Procedures. Benefits and Economics of Negotiated Settlements, Win-Win Philosophy.

  • Negotiated Settlement of the Claim: Each party has “expectations” linked directly to its own perception of one’s and other’s strong and weak points. You have the job to change the “expectations” of the other party - How Expectations can be Changed?

  • Pre-Negotiation Planning : Detail requirements and analysis of the contractor’s estimate. Contractor’s cost and price data. Audit of Contractor’s cost data. Preparing independent estimates. Sources for independent estimates. Establishing flexible negotiation strategies.

  • Conducting Negotiations. Steps in Negotiation.

  • Some Effective Negotiation Tactics and Tricks People Use : Consider using them, Countering them.

For Latest Program Schedule Email:

     cpp304@EuroTraining.com

REGISTRATION INFORMATION

  1. Please complete the Registration Form (Available at http://www.eurotraining.com/etl-reg.html) and FAX to UK +44 207 6811444 or Email to: euro@eurotraining.com

  2. Fee is £2250 (USD 4200) per participant includes Course Materials, Certificate, Refreshments and Lunch.

  3. Accommodation is not included in Program fee. Special rates will be available at venue hotel for the participants.

  4. Program Fee information is available by Emailing:  fees@eurotraining.com. Fee is payable by Bank Transfer or Bank Draft in favor of the local representative office.

  5. Early Registration & Payment discount is 10% - if registration and fee payment is made at least 45 days before start of the program.

  6. Fee includes Course Materials, Certificate/s, Refreshments and Lunch. Program Timings are 8:30 AM to 2:30 PM but on some days (to be announced by instructor/s) you may be asked to attend from 3:00 PM to 7:30 PM. For First Day Program Timings see your Joining Instructions.

Claims Management And Negotiating Win-Win Settlements CPP304

Contact: Mr Harry Miller, General Manager

FAX (UK) Fax : +44 207 6811444

FAX (USA) +1 650 6492689

UAE Dubai Fax +971 84 481032

www.EuroTraining.com

www.EuroTrainingUK.com

Email: euro@eurotraining.com  or   euro@eurotraining.com

Registration Form available at http://www.eurotraining.com/etl-regn.html

 

More Training Programs...

2008  2009  Auditing  CAD-EDMS  Contracts  ENERGY   ENGINEERING   Environment   Finance   HRD   Intellectual Property   IT   Knowledge Management   Maintenance  Management   Marketing   Petroleum Industry   Project  Procurement   Quality   Safety  Registration INFO

Registration Form    Fee Schedule     About Euro Training Limited & Programs    www.EuroTraining.com   www.EuroTrainingUK.com